The 2012 P3010 base order covered 78 light rail vehicles. Later options changed the numbers. Here is how to read the documents together.
The base order and the ceiling
Metro’s October 2013 update describes the contract approval in April 2012 and identifies 78 new cars in the base order. Four options created a possible total of 235 cars. The two figures answer different questions. One describes the initial order. The other includes the available options.
Follow the executed options
The same update says the board authorized options for 97 additional cars in July 2013. The April 2015 delivery report distinguishes that stage from later recommendations. To follow the project accurately, record the action verb next to every figure, then check the delivery and acceptance records separately.